Because of the high profile nature of the proposed Hubble Middle School
relocation, District 200 has had requests for clarifying information. With
that in mind, the following myths vs. facts are presented. The professionals
listed below contributed the information contained in this document. For more
information on this topic, visit the District 200 web page at
www.cusd200.org.
|
The New Middle School
|
|
Myths
|
Facts
|
|
The District has not considered all options for relocating or renovating
Hubble.
|
|
|
Renovating Hubble is the least expensive option.
|
-
New school design based on programs offered (186,000 sq. ft.):
$46.8 million, plus $7.6 million for property = $54.5 million total
project.
-
Renovating Hubble based on programs offered (includes small
addition and phased construction): $55.7 million total project.
-
Any renovation of Hubble would have to be phased over several
years.
-
Current stormwater management regulations would be in effect
for any renovation that increases the footprint of the
building, thus increasing costs.
-
The cost of the new school would be partially offset by the
sale of the existing Hubble site.
-
Tax dollars generated by the redevelopment of the Hubble
site would be lost if the existing Hubble is renovated.
|
|
Myth
|
Fact
|
|
The Board’s delay in purchasing the Herrick Road site cost taxpayers $3
million.
|
-
The $4.5 million sale price discussed in 2002-03 was for 10.4 acres
or $432,692 an acre.
-
The current contract for $7.6 million is for 18.6 acres or
$408,602 an acre.
|
|
The contract for the Herrick Road property was negotiated by District
personnel who are not qualified real estate brokers.
|
-
The contract was negotiated by the District’s outside counsel, Ares
Dalianis, of the Chicago law firm of Franczek Sullivan, in
consultation with a qualified appraiser holding the MAI designation
(Member, Appraisal Institute), the highest professional recognition
for a real estate appraiser.
-
The purchase price was agreed to using data on 19 sales of
comparable properties in the area.
|
|
The district has hidden information about the contract and the
negotiations for the middle school site.
|
|
|
There are unreported contingencies in the contract for the Herrick Road
property.
|
-A positive risk assessment study, which has been delivered.
-An NFR letter from the Illinois EPA.
-A successful referendum.
-soil test, engineering studies and report
-flood plain, flood hazard or wet land area
-archeological survey
|
|
There were not enough soil samples taken to adequately judge the
environmental safety of the site.
|
-
When the next round of testing is completed on April 19, 2007, there
will have been 56 environmental soil samples taken and analyzed,
approximately three per acre. The IEPA has reviewed all soil samples
collected and approved the current Work Plan.
|
|
Warrenville will not contribute any money toward the relocation of
Hubble to that community.
|
|
|
Myth
|
Fact
|
|
There will not be as much usable space in the new school as exists in
the current Hubble.
|
-
The new school is smaller in square feet, but the new design will do
more in less space.
-
The smaller footprint will save significant operating dollars each
year.
-
The new school was designed in conjunction with faculty and
staff to efficiently accommodate the needs and program of the
middle school.
|
|
The new school will not have multiple gyms, auditoriums, and other
amenities that Hubble has.
|
-
The program driven middle school design includes a large gym, a
small gym, and a fitness center.
-
The plan also includes spaces that Hubble does not have, e.g.,
drama classroom, presentation/lecture room, commons area for each
grade.
|
|
The Herrick Road property identified for a new middle school is on a
flood plain.
|
-
The most current versions of the FEMA and DuPage County Floodplain
maps clearly document that the property is not located in a
floodplain area.
-
The property was on the edge of a historical flood plain.
(Historical refers to 120,000 to 10,000 years ago.)
-
Wheaton Warrenville South High School sits on the edge of the
same historical flood plain.
|
|
Land development costs and infrastructure costs are not included in the
$46.8 million estimated school cost.
|
|
|
A stormwater detention pond to be located on vacant BP owned property
adjacent to the proposed school site will contaminate the school’s water
supply.
|
-
Stormwater runoff and groundwater migrates from the north to the
south in this area. The school will be located north of the BP
‘buffer’ property and north of the proposed stormwater detention
pond.
-
Locating the detention pond in an easement on the adjacent, vacant
BP property frees up two to three acres of land on the school site
for other student oriented purposes, such as athletic fields.
-
The City of Warrenville negotiated the shared stormwater
management easement agreement with BP specifically to enhance
the usability and safety of the proposed school site.
|
|
Myth
|
Fact
|
|
Water on the proposed school site is not safe to drink.
|
-
The new school would be connected to the City of Warrenville’s
municipal water system for drinking and fire protection purposes.
-
Regular required testing confirms that the City of Warrenville
municipal water in full compliance with the drinking water
standards established by the Federal Safe Drinking Water Act.
-
If for any reason the City’s municipal well system becomes
contaminated, the City may access and distribute Lake Michigan
water.
|
|
Eight feet of soil need to be removed from the site before construction
can start.
|
-
Substantial soil testing has been completed that indicates the soil
is structurally sound and well within industry standards.
-
Only one of the soil boring locations was recommended for soil
removal beyond normal expectations. That removal is based on
geotechnical concerns, not environmental.
-
This boring is far from the proposed location of the new
building.
|
|
An emergency access road is planned due to the property’s proximity to
the BP Campus.
|
-
The secondary emergency vehicle access road is being provided to
insure that fire trucks and ambulances can access the school site
should the main entry become blocked for any reason.
-
Most municipalities and fire departments require multiple means of
emergency vehicle access to new projects such as this.
|
|
Busing costs will increase if the new school is built in Warrenville.
|
|
|
There is not adequate space in the community to relocate the non-school
functions currently held at Hubble.
|
-
The District will work with the Wheaton Park District and other
renters to relocate their programs to other schools. Outdoor
activities can be relocated to other fields, the high school
fieldhouses, and the high school stadiums.
-
All current users of Hubble can be accommodated at other District
200 locations. In addition, the redevelopment of Hubble will
include open space.
-
The District is also in discussions with the park district
regarding the installation of an artificial surface on the
football field at Monroe Middle School, a project that would
open up the field for more activities.
|
|
Myth
|
Fact
|
|
The District has inflated the potential tax benefits of developing the
Hubble property.
|
|
|
District 200 offered a no bid contract to architects.
|
-
Legat Architects was selected through an interview process. State
law requires school districts to select architects based on their
performance and prohibits them from seeking formal or informal fee
estimates prior to their selection.
-
Following selection, fees are negotiated for each project.
|
|
Hiring architects to design a new school and prepare bid documents
before a successful referendum is a waste of taxpayer money.
|
|
|
The architect’s fee for the project is $3 million.
|
-
The fee will be approximately $2.6 million based on 6.75 percent of
the actual construction cost.
-
In addition to the architect services, the fee includes services
of civil engineers, structural engineers, and mechanical,
electrical, plumbing and fire protection engineers, a total of
more than 25 licensed professionals.
|
|
It will take the Illinois EPA more than two years to complete its study
of the site and to decide if it will issue an NFR letter.
|
-
After the EPA has received the results from additional testing and
samples, based on the Work Plan the agency has approved, it takes 90
days or less to act on the NFR request. All tests and sampling will
be completed and analyzed by early May and the results will be
submitted in a report required by the IEPA. The timeline starts
then.
|
|
The decision to change Hubble’s attendance boundaries has already been
made.
|
-
A committee is working to study this possibility and will make
recommendations to the Board of Education. Parents and community
members will have ample opportunity to respond to the
recommendations before any decisions are made.
-
The committee’s preliminary review of options indicates the need
for relatively few boundary adjustments.
|
|
Myth
|
Fact
|
|
The City of Warrenville has adopted three ordinances to address issues
on the proposed school site.
|
-
Ord. 2300 has nothing to do with the proposed school site. It
relates only to the Cantera Development.
-
Ord. 2301 was adopted to support an agreement with BP to provide
land for stormwater detention and an emergency access easement for
the middle school project.
-
Ord. 2303 has nothing to do with the proposed school site. It
supports an agreement with BP that gives the City the right to
offer to purchase BP owned land at the northwest corner of
Herrick and Warrenville Roads. The City wanted this agreement to
ensure that any future development of the property would be of
high quality.
|
|
The BP Naperville Campus
|
|
The BP Naperville Campus is primarily a petrochemical research facility.
|
-
The BP complex is primarily office based. Only 33 percent of the
1600 people who work on the site are involved in research. Of those
involved in research, only a third work directly with chemicals.
-
Future research will become more technology oriented, with
increased emphasis on computer modeling and simulation.
-
DePaul University is housed in the building closest to the
proposed school site as an adjunct campus.
|
|
Barrels of chemicals are stored for indefinite periods of time on the BP
Campus.
|
|
|
BP has leaking underground storage tanks (LUST’S) that contaminate the
soil and water supply.
|
-
Records indicate BP has a history of responding to and dealing with
leaking UST’S in a timely manner that satisfies IEPA regulatory
requirements.
-
IEPA records indicate current issues are being properly and
actively managed.
-
Underground water migrates south of the BP Campus; therefore, a
water migration pattern to the proposed school site does not
exist.
|
|
Myth
|
Fact
|
|
There were more than six million pounds of hazardous chemical emissions
from the BP Campus over a ten-year period.
|
-
Virtually all of the emissions from the BP Naperville Campus are the
result of burning natural gas—the same natural gas that is burned in
water heaters and stoves in resident’s homes.
-
Hazardous chemical emissions from the Naperville Campus are
similar to those that come from gasoline vapors. In 2005, these
totaled about 2,300 pounds.
-
Hazardous chemicals found in the waste generated by research
activities are driven off campus by licensed waste haulers and
disposed of at EPA-permitted facilities designed to handle such
waste.
|
|
BP stores more chemicals than the EPA allows.
|
|
|
BP has significant environmental impacts as indicated by ISO 14001
Environmental Management System.
|
-
ISO 14001 EMS is an internationally recognized process that
companies use to develop a management approach to any environmental
concerns that exist.
-
Under this system, BP has identified the impact that could
occur and established programs and processes to address them.
|
|
Emissions from volatile organic compounds (VOC’s) pose a hazard to
neighbors of BP.
|
-
The U.S. Environmental Protection Agency says the VOC’s disperse in
the air and those from BP are indistinguishable from those emitted
from traffic near the facility, including I88.
-
It is common for electricity cogeneration plants, such as the BP
combustion turbine and boilers, to have an occasional malfunction
that results in a reported excess emission event.
-
A Boelter Associates report confirmed that air emissions from BP
are not a significant risk to the proposed school site.
-
There is little difference between the magnitude of toxic
chemical emissions at the 178-acrea BP Campus and an average
gas station.
|
|
Myth
|
Fact
|
|
BP doesn’t want property it owns (or did own) developed because it is
known to be contaminated.
|
-
BP has no indication whatsoever that either of the ‘buffer’
properties north of Warrenville Road have environmental
contaminants.
-
A Phase I study of the property sold to the Forest Preserve
indicates no contaminants.
-
BP has repeatedly stated their reason for maintaining the
‘buffer’ properties as open space is to keep traffic from
increasing.
-
BP has never used the property in the ‘buffer’ areas for any
purpose.
|
|
The deed restrictions BP imposed on property it sold to the Forest
Preserve evidence environmental concerns for nearby properties.
|
-
A Phase I environmental study of the site, which included an
assessment of the BP Campus, found no environmental issues.
-
The property has never been used by BP; it was most recently used
for farming.
-
The sale of the property is a win-win for both BP and the Forest
Preserve. It completes the Herrick Lake Forest Preserve site,
remains a buffer for noise pollution, and insures no future
development on site.
|
|
Related Topics
|
|
The school district determines how the Hubble site will be developed
when the new school is built.
|
|
|
Cook County requires an NFR letter from the IEPA before a new school can
be constructed, while DuPage County does not.
|
-
The EPA requires an NFR letter on Cook County property intended for
school use only when a Phase I and a Phase II study confirm
the presence of a contaminant of concern.
-
This requirement does not impact the proposed school site, which
is in DuPage County. However, if the Herrick Road property were in
Cook County, the results of the two Phase I environmental surveys
would have satisfied Cook County requirements.
-
However, the Phase I and Phase II studies on the proposed school
site did not find contaminants of concern.
|
|
The renovation of the historic Lindblom High School in Chicago was done
at a significantly lower square foot cost than the estimates for
renovating Hubble.
|
|